APMG Agile Foundation Practice Exam 2025 – 400 Free Practice Questions to Pass the Exam

Question: 1 / 400

What is a sprint retrospective meeting?

A planning session for the next sprint

A meeting to celebrate success

A meeting held after a sprint to reflect on the process and discuss improvements

A sprint retrospective meeting is a crucial component of the Agile framework, particularly in Scrum methodology. This meeting occurs at the end of each sprint and serves as an opportunity for the team to reflect on the past sprint's processes and outcomes. During the retrospective, team members discuss what went well, what did not go well, and how they can improve in future sprints. This introspective approach encourages continuous improvement within the team, allowing them to identify actionable items for enhancing their effectiveness and productivity.

The focus is on fostering an environment of open communication and collaboration, where team members can share insights and feedback constructively. By regularly conducting these meetings, teams can adapt their practices, optimize their workflow, and ultimately deliver higher quality products.

In contrast, the other choices do not accurately depict the purpose of a sprint retrospective. Planning for the next sprint, while essential, is part of a different meeting called the sprint planning meeting. Celebrating success is important but is not the central aim of the retrospective; rather, it focuses on learning and improving. Lastly, reviewing completed tasks for documentation does not encompass the reflective and improvement-oriented nature of the retrospective. Instead, the retrospective emphasizes process evaluation and team development.

Get further explanation with Examzify DeepDiveBeta

A review of completed tasks for documentation