Which of these is NOT a phase in the DSDM process?

  1. Feasibility

  2. Evolutionary Development

  3. Engineering

  4. Post-Project

The correct answer is: Engineering

The DSDM (Dynamic Systems Development Method) process consists of several distinct phases that guide a project from inception to completion. The phases include Feasibility, which assesses whether the project is viable; Evolutionary Development, where the product is built incrementally through iterations; and Post-Project, which involves evaluating the project after its completion to capture lessons learned and ensure continuous improvement. The term "Engineering" is not recognized as an official phase within the DSDM framework. While engineering practices may be incorporated into the development work, they are not defined as a standalone phase in the DSDM process. This is why identifying "Engineering" as the option that does not belong among the specified phases highlights its absence from the formal structure of the DSDM methodology. Understanding the defined phases of DSDM is essential for grasping how the framework organizes and manages agile projects.